Business DEX (UK_Defence056):— support_cost_breakdown | Date: 2010/03/11 12:08:40 Revision: 1.7 |
The information requirements table for the Support Cost Breakdown DEX is shown below:
Information requirement |
Business Object(s) |
---|---|
Information that is used to define the message that performs the transmission of the Support Cost Breakdown information between the source and destination UK_Defence processes. | Message, Record. |
Definition of the structure of a cost breakdown. | Cost Item Type, Cost Item Relationship |
Identification of the PSE elements for which the support cost breakdown has been derived, including all the assumptions, requirements, and constraints from which the SC and SSD were derived. (The “CDAL” or “Cost Data and Assumptions List” – a subset of the “MDAL” or “Master Data and Assumptions List”). | Assumption, Constraint, Requirement, Support Component |
Identification of the analysis that defined the support cost breakdown. | Cost Analysis |
Identification of the support cost breakdown. | Support Cost Breakdown |
Identification of each predicted support cost type within the support cost breakdown. | Cost Item Type |
Specification of the time at which, or the period during which, the cost is expected. | Cost Item |
Reference to the corresponding actual costs and when they are incurred. | Activity Resource Usage Cost |
Budget allocation: “CDEL”, “RDEL”, or “IRDEL” (“Capital Defence Expenditure Limit”, “direct Resource Defence Expenditure Limit”, and “Indirect Resource Defence Expenditure Limit”). | Cost Item Type, Budget |
Period covered by the support cost breakdown. | Support Cost Breakdown, Cost Item Type, Cost Item |
Context of the support cost breakdown. (annual budget, initial investment appraisal, etc). | Support Cost Breakdown |
Table 1 — Support Cost Breakdown information requirements
© UK MOD 2010 — All rights reserved